mstrlucky74
Senior Member
- Location
- NJ
I know this is general but standard install scenario, wide open space with 8’ ceiling and attaching emt with KX clip is doing 100’ of ¾” EMT with ss fitting in 8 hours out of the question. Say there are 5- 4” boxes in the run. 8 hours wouldn’t include installing the boxes but obviously you need connectors and have to term the conduit. Thanks.