Alwayslearningelec
Senior Member
- Location
- NJ
- Occupation
- Estimator
Ok, I'm sure I'm gonna catch grief but I would like to know the diffent scenerios for running conduit risers in a new construction building through several stories Yes I have never worked in the field but I bust my a$$ in the office working 11 hour days at not a lot of $$$$$. I'm always spending my spare time trying learn. Well, I hope I'm worthy:grin:... The following is what I know...
1. Open shaft throughout all the floors??? How are the conduits supported? Box with cable supports?
2. They will pour floor then your have to sleeve all conduits. I guess you still need boxes and cables supports.
3. Unistrut attached to walls supporting conduits.
What is most common method? Thanks
Any pics would be greatly appreciated along with input.
1. Open shaft throughout all the floors??? How are the conduits supported? Box with cable supports?
2. They will pour floor then your have to sleeve all conduits. I guess you still need boxes and cables supports.
3. Unistrut attached to walls supporting conduits.
What is most common method? Thanks
Any pics would be greatly appreciated along with input.