Got a call to 'finish' a job that the first EC had walked...(or ran)...away from because they didn't have time to finish the job. Go Figure.
Anyway, the commercial kitchen contains a stainless steel table/sink basin that is located in the center of the room and the occupant had requested that a receptacle be installed on the opposite side of the table from where the basin is located.
The problem is that the first EC installed 1-1/4 SCH40 Conduit from the panel, under a poured concrete foundation, and it is stubbed up at the end of the table base. Why they installed 1-1/4 I have no idea.
My question is: Any ideas on terminating this conduit so 1/2 conduit can then be run up to the outlet j-box? I have considered different types of boxes, but i'm not sure it would look very 'neat and workmanlike' in the end. And what are the Code issues?
Thanks,
Jemsvcs
Anyway, the commercial kitchen contains a stainless steel table/sink basin that is located in the center of the room and the occupant had requested that a receptacle be installed on the opposite side of the table from where the basin is located.
The problem is that the first EC installed 1-1/4 SCH40 Conduit from the panel, under a poured concrete foundation, and it is stubbed up at the end of the table base. Why they installed 1-1/4 I have no idea.
My question is: Any ideas on terminating this conduit so 1/2 conduit can then be run up to the outlet j-box? I have considered different types of boxes, but i'm not sure it would look very 'neat and workmanlike' in the end. And what are the Code issues?