Johnhall30
Senior Member
- Location
- New Orleans, LA
- Occupation
- Engineer
Electrical panel is mounted on top of a flat roof section of a 5 story building. RMC conduit is running on top of the roof surface supported on dura-block 3-4 inches above the roof membrane. The conduits pass directly under and in front of the electrical panel and are technically within the working space of the panel.
This is a new construction project. Should there be a platform installed in front of the electrical panel, over the conduits, to make a cleaner working space?
Code opinions?
This is a new construction project. Should there be a platform installed in front of the electrical panel, over the conduits, to make a cleaner working space?
Code opinions?