keith gigabyte
Senior Member
- Location
- New Kensington, Pa
My background is residential rewires, commercial new construction, and industrial controls install and troubleshooting
I recently looked at a job to install a new service at a residence. Existing conditions...old entrance cable, old meter base, new load side wire form meter base, new 100 amp plug on panel, solar inverter and 30 amp disconnect switch (maybe 1-4 years old) greenfield from inverter outside to existing panel in basement. wires from inverter are stuffed under the same lugs as the load side wires from meter socket. How does the synchronizing of phases occur from solar unit and power company?
I am familiar with synchroscopes and synchronizing multiple generators from my industrial background. so just tying wires together with spilt bolts doesn't seem right to me.
My question is how do I go about replacing the service; line side and meter base, tie the solar inverter into the new panel.
I recently looked at a job to install a new service at a residence. Existing conditions...old entrance cable, old meter base, new load side wire form meter base, new 100 amp plug on panel, solar inverter and 30 amp disconnect switch (maybe 1-4 years old) greenfield from inverter outside to existing panel in basement. wires from inverter are stuffed under the same lugs as the load side wires from meter socket. How does the synchronizing of phases occur from solar unit and power company?
I am familiar with synchroscopes and synchronizing multiple generators from my industrial background. so just tying wires together with spilt bolts doesn't seem right to me.
My question is how do I go about replacing the service; line side and meter base, tie the solar inverter into the new panel.