I have always calculated commercial lighting as a continuous duty load for branch circuit and overcurrent protection sizing. I have also considered it to be continuous duty when calculating commercial services.
Today, an associate is arguing that it is not required to be multiplied by 125% for service calculations.
In looking at NEC 220, I can't argue with him. Anyone have input here? I have hit all continuous duty loads with 125% for load calcs for a long time. If I've been wrong, at least it's been an error on the conservative side.
Thx for any input and happy 4th to all
Today, an associate is arguing that it is not required to be multiplied by 125% for service calculations.
In looking at NEC 220, I can't argue with him. Anyone have input here? I have hit all continuous duty loads with 125% for load calcs for a long time. If I've been wrong, at least it's been an error on the conservative side.
Thx for any input and happy 4th to all