1. We want to run (2) sets of 4#600KCM copper, 1#3G, 4" EMT for a distance of 300 feet from elec. rm-A to elec. rm-B. Estimate how much does it cost including labor cost? Are there any free online electrical estimate calculators that we can use?
2. We have 4,000A main CB SWBD, 480V-3PH, 4W. We want to add 1,200A breaker (the swbd already has space for 1,200A CB). Can electrician install this breaker without shutdown the main? Usually, how long does it take to complete this work? I assume they must have special certificate to do this "hot" work? What is it?
2. We have 4,000A main CB SWBD, 480V-3PH, 4W. We want to add 1,200A breaker (the swbd already has space for 1,200A CB). Can electrician install this breaker without shutdown the main? Usually, how long does it take to complete this work? I assume they must have special certificate to do this "hot" work? What is it?