Could anyone help with the following please:
At maximum demand levels of between 500KVA and 999KVA a consumer can elect to take their supply at either LV or HV.
Has anyone done a design note comparing the relative merits of each approach such as:
Capital cost
Running / maintenance costs
Utility charges / Tariffs
Spatial requirements
Restrictions on plant space location
Program
Any help most appreciated.
At maximum demand levels of between 500KVA and 999KVA a consumer can elect to take their supply at either LV or HV.
Has anyone done a design note comparing the relative merits of each approach such as:
Capital cost
Running / maintenance costs
Utility charges / Tariffs
Spatial requirements
Restrictions on plant space location
Program
Any help most appreciated.