I have yet to install a Large Generator transfer switch. Seems no different from a small portable transfer switch. Though I have to bid this and was hoping to get some idea on how many labor hours this would take some of you.
Its a 16 circuit 100 amp transfer switch for this unit https://www.generac.com/all-product...-7172-16-circuit-transfer-switch-wifi-enabled
meter is a Recessed 3r stainless meter base. with panel directly behind it and the generator is within 6' of the meter.
Panel is directly behind.
Thinking from start to finish 16hr.
I passed on a few of these since everyone want a bid and not T&M and I don't want to eat into my money, by learning. So I good idea would help.
Thanks
As far as access to equipment. I was basing it on sheetrock removal from both stud bays.
Its to far away to see so I was using that as a base then charge more if needed.
Its a 16 circuit 100 amp transfer switch for this unit https://www.generac.com/all-product...-7172-16-circuit-transfer-switch-wifi-enabled
meter is a Recessed 3r stainless meter base. with panel directly behind it and the generator is within 6' of the meter.
Panel is directly behind.
Thinking from start to finish 16hr.
I passed on a few of these since everyone want a bid and not T&M and I don't want to eat into my money, by learning. So I good idea would help.
Thanks
As far as access to equipment. I was basing it on sheetrock removal from both stud bays.
Its to far away to see so I was using that as a base then charge more if needed.