donburde
Member
- Location
- Fort Lauderdale, FL
I am beginning the underground in a maintenance shop. Everything will be run in sch 40 PVC. There is a 10" slab inside of a metal building. My interpretation of 300.5 is that I can run my underground conduits directly under the slab in the pad. The maintenance shop is for large trucks and bulldozers so obviously there will be heavy vehicles in the shop although I don't see anywhere that would prohibit my from running my conduit 0" below the slab. Any comments?