andy32821
Member
- Location
- Orlando, Fl
- Occupation
- Automation
Hi,
I need to install a ct shorting block on an existing GE EPM 9900 energy meter. Most of the commercially available shorting blocks direct me to tie together and ground the ct negative leads. The GE manual recommends shorting blocks as an option, but the installation block diagram of the energy meter show 3 completely independent ct's. (3 phase 4 wire wye system.)
Is there any advantage to shorting the negative leads? Any way this could affect the meter?
I'm installing the shorting block on the next shutdown, I don't want to cause an additional shutdown to correct the wiring. The goal is to be able to replace the meter in the future without a power outage.
Thanks,
Andy
I need to install a ct shorting block on an existing GE EPM 9900 energy meter. Most of the commercially available shorting blocks direct me to tie together and ground the ct negative leads. The GE manual recommends shorting blocks as an option, but the installation block diagram of the energy meter show 3 completely independent ct's. (3 phase 4 wire wye system.)
Is there any advantage to shorting the negative leads? Any way this could affect the meter?
I'm installing the shorting block on the next shutdown, I don't want to cause an additional shutdown to correct the wiring. The goal is to be able to replace the meter in the future without a power outage.
Thanks,
Andy