Custom Expedited Switchgear & Switchboard

JLB75

Member
Location
Arizona
Occupation
Partner - Manufacturer
We are now manufacturing hard to get 400-4000amp switchgear and delivering in all 50 states and Canada.

UL 891

4-6 weeks
 

petersonra

Senior Member
Location
Northern illinois
Occupation
engineer
I have found of late it is not real hard to get something workable as long as you are not picky about brands or features, at least for control panels.

This has led to some odd designs but you do what you have to do to get by.
 

Tainted

Senior Member
Location
New York
Occupation
Engineer (PE)
We are now manufacturing hard to get 400-4000amp switchgear and delivering in all 50 states and Canada.

UL 891

4-6 weeks

In NYC lead-time for those switchboards are 40-60 weeks unfortunately.

Do you guys manufacture NYC compliant switchboards? NYC has extremely VERY specific requirements for switchboards.
 