Dedicated space

Status
Not open for further replies.

nizak

Senior Member
With a flush mount load center installed between wall studs, is the wall cavity below considered dedicated space?

Surface to be drywalled.

Or does that only pertain to a surface mount application?

Water lines will be passing horizontally through stud cavity underneath .

Haven't came across this situation, code doesn't differentiate between surface and flush mounting.

Thanks much
 
So it pertains to both mounting applications?
It's working space in front of the panel. Even the panel itself cannot be in the working space. Nothing below it, nor to the sides, count against your working space.

Every panel, regardless of mounting configuration, has the same requirements
 

Attachments

  • 20210811_095312.jpg
    20210811_095312.jpg
    229.4 KB · Views: 8
It's working space in front of the panel. Even the panel itself cannot be in the working space. Nothing below it, nor to the sides, count against your working space.

Every panel, regardless of mounting configuration, has the same requirements
The question is about dedicated equipment space not working space.
 
It's working space in front of the panel. Even the panel itself cannot be in the working space. Nothing below it, nor to the sides, count against your working space.

Every panel, regardless of mounting configuration, has the same requirements

Looks like it’s measured from the opening if its enclosed.


Sent from my iPhone using Tapatalk
 
Status
Not open for further replies.