32Lateralus
Member
- Location
- West Coast
- Occupation
- Electrical
Let's say I have an existing facility, and we are doing some new work there.
We have solid as-builts with calculated loads. We could do a 30-day meter study and apply 125% but time doesnt really allow.
Ive often seen calcs done where it just takes the bulk panel as-built load, maybe some removed load, and then calcs all the new load separately with it's own stand-alone demand factors not accounting for existing (the more conservative approach it seems) and adds it to the calculated as-built load. But are we able to group existing loads into our demand factors?
For example:
Lets assume a 100A panel, 70A calculated load. The as-builts show over 10KVA of receptacle load and some existing remainder at 50%. When I add new receptacle load, and I able to take it at 50% as well? Same for adding a motor that isnt the largest compared to existing. Am I able to use these demand factors from existing loads in my calc?
We have solid as-builts with calculated loads. We could do a 30-day meter study and apply 125% but time doesnt really allow.
Ive often seen calcs done where it just takes the bulk panel as-built load, maybe some removed load, and then calcs all the new load separately with it's own stand-alone demand factors not accounting for existing (the more conservative approach it seems) and adds it to the calculated as-built load. But are we able to group existing loads into our demand factors?
For example:
Lets assume a 100A panel, 70A calculated load. The as-builts show over 10KVA of receptacle load and some existing remainder at 50%. When I add new receptacle load, and I able to take it at 50% as well? Same for adding a motor that isnt the largest compared to existing. Am I able to use these demand factors from existing loads in my calc?