Fjahnke@premiercorp.net
New member
- Location
- Minneapolis,minnesota
Our company has a high rise condo project. The developer wants to have an electrical car charging unit for each parking space. There are 218 unit parking spaces. My question is that is there a demand/ diversity factor that you can apply to the total connected load. They obviously won’t all be used 100 % of the time. I am thinking like the demand factor for electrical ranges in the units. Is there any code articles that apply?