NEC User
Senior Member
- Location
- Marlboro, NJ, USA
I'm working on a new commercial facility (not a dwelling unit) that will have 2 large roof top units and several other large air handling units and then a lot of small motor loads. I'm trying to figure out where in the NEC it says how I can calculate demand loads for these motors.
They all won't be on at the same time. Are my supposed to calculate my demand load as 125% of the largest motor and 100% of all other motor loads? Is there a diversity factor I should use?
I tried looking at NEC 220.50 and 430.24, 430.25, and 430.26.
They all won't be on at the same time. Are my supposed to calculate my demand load as 125% of the largest motor and 100% of all other motor loads? Is there a diversity factor I should use?
I tried looking at NEC 220.50 and 430.24, 430.25, and 430.26.