Opinion wanted on approach. If you had a portion of a floor being fully demolished and renovated as shown in pic would you.

  1. Just survey, trace and safe off and disconnect electrical circuits without removing every fixture/receptacle individually so they can be demolished/removed by demo company or laborers. I see not reason to remove each light/receptacle.

Sure there would be circuits in the construction area that might feed adjacent areas and one would have to modify/bridge those circuits.
 

Attachments

  • Capture.PNG
    Capture.PNG
    1.2 MB · Views: 15

Buck Parrish

Senior Member
Location
NC & IN
Just survey, trace and safe off and disconnect electrical circuits without removing every fixture/receptacle individually so they can be demolished/ Recycled

That exam room may have a circuit going under the slab and then back up to the chair.
 