I have a customer who had a union electrician friend of his help him with his wiring in his new house up here in maine. For starters not positive if his friend is licensed or not or just has his helpers, however he ran all circuits to a 12x12 junction box in the ceiling and feom the junction box he ran a 2 1/2" emt to the main panel. My question is once you account for derating calculations of approximately 20 circuits give or take this is reqyiring me to run a #10 for 15a circuits and #8 for 20a circuits is there a simplied and way less expensive solution to runing these circuits? I've considered just running feed wires through the conduit to a sub panel but even in thay case the entire place is already drywalled and finished off? Never ran into this situation so just trying to brainstorm thanks.