I have a small load on the end of a very long run. (4 amp / 600') Wire is already oversized 3x to deal with the distance. This run also has 4 current carrying conductors in the same conduit for the first 300' Boss is telling me that the 80% needs to be taken off before the voltage drop calculation, which might cause the wire to be upsized again. (significantly more expensive) I have always assumed that upsizing for Voltage drop "covered" you on the fill, as if it was a non-coincidental thing. Is there anywhere in the code that spells out this order of operation?