Designer69
Senior Member
If an electrical contractor is selected as the winning bidder for a project at a certain cost that they bid but then later during construction it is decided that an elec. equipment is downgraded to something that costs $20K less, does the Elec. Contractor reimburse the General Contractor for this difference or do they just say nope, doesn't matter they get what their initial bid was on original drawings regardless of what is installed.
Just want to understand how this generally works, Thanks.
Just want to understand how this generally works, Thanks.