sokkerdude
Member
- Location
- Arkansas
I am doing a design-build project that has in its spec the following . "That you are not to start construction until you have a 100% approved prints."
Well the owners and general started the building with 50% complete drawing.
My question is sence we started the construction at the general and owner demand, can I call the drawing we started with 100% approved prints for the
purpose on of changes in cost, that are now happening has a result of not doing the desing work on the front end.
Well the owners and general started the building with 50% complete drawing.
My question is sence we started the construction at the general and owner demand, can I call the drawing we started with 100% approved prints for the
purpose on of changes in cost, that are now happening has a result of not doing the desing work on the front end.