carryyourbooks
Member
i recently completed a quad plex.  there were a total of (5) 125 amp services for this building -- (4) apartments, (1) house panel for ext. lighting and access gate.  i put mains in all the panels.  i set up my service as follows from the gound up:  (5) panels; connected to (5) meter sockets via offset nipples; connected to gutter box.  out of the gutter box i went up with (3) 400 mcm's.  i did a load analysis and came up with almost 400 amps of load after lighting, heat, etc.  no gas to be used at all here.  i bonded my neutral and gec in the gutter box and installed interlock system as required.
here's the question:
did i maximize my savings? could i have done this job cheaper, more efficient? if all my panels were 125 amps, did i have to go to 400 amps on the riser? i typically don't do alot of apartments, so i am in the dark here. could i have saved $$$ by using a meter bank?
thanks for the advice.
	
		
			
		
		
	
				
			here's the question:
did i maximize my savings? could i have done this job cheaper, more efficient? if all my panels were 125 amps, did i have to go to 400 amps on the riser? i typically don't do alot of apartments, so i am in the dark here. could i have saved $$$ by using a meter bank?
thanks for the advice.
				