Hi
1) We have 12 nos 1500 KVA,11 KV/400 V transformers connected via ring main units using 3 core X 300 mm2 cable. It is supposed to feed from both sides like a ring (British standard). Now the issue is, in the first contract the scope was to energize these 12 transformers only. Now we are going to give another contract to complete this loop. The problem is 300 mm2 cable is not readily available. So can we use 2 nos of 120 mm2 in parellel to complete this loop. Is there any code violations?
2) The distribution panel boards we are using here do not use any GFCIs for receptacles circuits or not with main incoming breaker. Is there any code requirements for personnel protection?
Thanks in advance
Siva (Djibouti)
1) We have 12 nos 1500 KVA,11 KV/400 V transformers connected via ring main units using 3 core X 300 mm2 cable. It is supposed to feed from both sides like a ring (British standard). Now the issue is, in the first contract the scope was to energize these 12 transformers only. Now we are going to give another contract to complete this loop. The problem is 300 mm2 cable is not readily available. So can we use 2 nos of 120 mm2 in parellel to complete this loop. Is there any code violations?
2) The distribution panel boards we are using here do not use any GFCIs for receptacles circuits or not with main incoming breaker. Is there any code requirements for personnel protection?
Thanks in advance
Siva (Djibouti)