Jesse7623
Senior Member
- Location
- eastern Mass
I'm working on a solar project where all the DC feeders are direct burial. On one end they are brought through underground piping into the recombiner, while the other end is brought up through a schedule 80 90° sweep onto a cab system. Is there somewhere in the code that indicates how far below grade, the pipe must extend before the cables may exit into direct burial?