I just bought a warehouse that needs some serious updating.
There are 5 floors including a Basement
I plan to Run Separate feeders to each Floor and each floor having its own Disconnect and Panel. Oh and its 3 phase.
So my question is can I run the feeders to the Disconnect on each floor then to a Main Lug Panel?...and do this for each floor?
Or do I have to have the disconnect means at the beginning of the circuit ( next to Main CT).
My goal with the disconects is to drastically reduce the amount of money Id have top spend on 5 panels with main breakers...(800 US bucks a POP)
Any Helps appreciated
There are 5 floors including a Basement
I plan to Run Separate feeders to each Floor and each floor having its own Disconnect and Panel. Oh and its 3 phase.
So my question is can I run the feeders to the Disconnect on each floor then to a Main Lug Panel?...and do this for each floor?
Or do I have to have the disconnect means at the beginning of the circuit ( next to Main CT).
My goal with the disconects is to drastically reduce the amount of money Id have top spend on 5 panels with main breakers...(800 US bucks a POP)
Any Helps appreciated