• We will be performing upgrades on the forums and server over the weekend. The forums may be unavailable multiple times for up to an hour each. Thank you for your patience and understanding as we work to make the forums even better.

Disconnect 3rd leg for G-GC Ground Check circuit?

Status
Not open for further replies.

PlasticFarmer

Member
Location
Ontario, Canada
Occupation
Industrial maintenance and equipment design
I am looking to do something unconventional and I cannot seem to find anything in the CEC for guidance. We have a 600V single phase machine that is used for underground mining work. In order to light up the feeder panels, a ground conductor monitoring (GCM) circuit must be closed at the load. It feeds a small current back up the ground of a Type G-GC feeder cable to verify its continuity to the feeder panel.

The simplest way that I can add this seems to be by running it through the unused 3rd leg of the disconnect, through a neutral link and the required zener diode and then into the ground. Throwing the disconnect would then tell the GCM module in the feeder panel to open/close the contactor. It seems fairly safe, as throwing the disconnect simultaneously kills the load and its feeder in series.

I have seen this done lots of times with an auxiliary contact added to a disconnect (thanks Square D) but the older equipment doesn't appear to accept one. Does anyone see a reason why using the empty third leg would not be acceptable? What part of the code if any would cover this?
 

tortuga

Code Historian
Location
Oregon
Occupation
Electrical Design
I am looking to do something unconventional and I cannot seem to find anything in the CEC for guidance. We have a 600V single phase machine that is used for underground mining work. In order to light up the feeder panels, a ground conductor monitoring (GCM) circuit must be closed at the load. It feeds a small current back up the ground of a Type G-GC feeder cable to verify its continuity to the feeder panel.

The simplest way that I can add this seems to be by running it through the unused 3rd leg of the disconnect, through a neutral link and the required zener diode and then into the ground. Throwing the disconnect would then tell the GCM module in the feeder panel to open/close the contactor. It seems fairly safe, as throwing the disconnect simultaneously kills the load and its feeder in series.

I have seen this done lots of times with an auxiliary contact added to a disconnect (thanks Square D) but the older equipment doesn't appear to accept one. Does anyone see a reason why using the empty third leg would not be acceptable? What part of the code if any would cover this?
I believe you are dealing with a Class 1 circuit, its probably okay but the wires need to have the same insulation rating as the 600V feeders. I believe its Section 16 of the CE code.

Rule 16-008 notes that Class 1 or Class 2 circuits installed in hazardous locations are also subject to the rules of Section 18.
Rule 16-010 specifies that remote control circuits to safety control devices where failure could cause a fire or a life hazard are to be considered and installed as Class 1 circuits.
 
Status
Not open for further replies.
Top