GerryB
Senior Member
- Location
- woodbridge, ct. USA
This is probably a POCO call and I am waiting for them to get back to me but they haven't yet. The job is an existing 3 family with the meters located inside in the center of the basement, 15 feet from the outside. Ridgid conduit, no disconnect. They can stay as is. We have to add a house meter. POCO usually wants all the meters together. It doesn't look as if I can add to the old existing meters so I will most likely run a new service for the house meter.
My question is can you put a disconnect outside or as soon as you enter the premises that would be ahead of the meter.
My question is can you put a disconnect outside or as soon as you enter the premises that would be ahead of the meter.