This is the situation. A new service with the service point (over 600V) originating on a customer owned riser pole terminated to the local Utilities provided pigtails. This is a primary metered service. From the riser pole to the customer owned transformer is 800? of 12470V service conductors, again customer owned.
Questions:
Is a disconnecting means (medium voltage fused switch) required by the N.E.C. on the primary service conductors?
If a switch is required, does the switch need to be located the at the riser pole?
What code article, if any, addresses this?
Thanks,
cey
Questions:
Is a disconnecting means (medium voltage fused switch) required by the N.E.C. on the primary service conductors?
If a switch is required, does the switch need to be located the at the riser pole?
What code article, if any, addresses this?
Thanks,
cey