codequestion
Banned
- Location
- MD, USA
I have incoming electric utiliity coming into service equipment with 2000 amps main breaker and trough.
On the trough there are eight disconnects. Six going to different tenan, one new going to another tenant and one future spare. The six disconnects are fused but the new one plan is saying non fused. Does the new disconnect be fused and article services apply or article outside feeder apply?
Sent from my SM-G935U using Tapatalk
On the trough there are eight disconnects. Six going to different tenan, one new going to another tenant and one future spare. The six disconnects are fused but the new one plan is saying non fused. Does the new disconnect be fused and article services apply or article outside feeder apply?
Sent from my SM-G935U using Tapatalk