dvcraven0522!
Member
- Location
- St. Louis
- Occupation
- Electrical Design
Good Morning - I am designing cables for temporary full generator back up with cam-locks. I have attached a spec. sheet for DLO cabling. I don't know much about this type of cable but we apparently have used this on previous designs.
In essence I plan on a 600 amp service with a manual transfer switch for the generator. Per the attached spec. I am not sure in the columns for amps what is meant by 1 & 2.
As an example for #4/0 indicates 260amps for (1) and (405 for (2). I would assume 2 cables. Is that correct?
Thank you for taking the time to review my question.
In essence I plan on a 600 amp service with a manual transfer switch for the generator. Per the attached spec. I am not sure in the columns for amps what is meant by 1 & 2.
As an example for #4/0 indicates 260amps for (1) and (405 for (2). I would assume 2 cables. Is that correct?
Thank you for taking the time to review my question.