I am feeding 120V, 2W, 100A from a UPS to a 120/240V panel. The customer wants to use a main circuit breaker. I want to use MLO. The UPS has a circuit breaker feeding this panel. The problem I have using the MCB in the panel is that I would be double lugging one terminal to install the jumper. Does anyone see a problem with this? The customer is specifying 1/0 cable for the feeder conductors. The panel is Cutler-Hammer. The MCB that the customer wants to use is 100A, 2P, BAB.