I was recently involved with a job where a customer's service cable (3-wire, single phase) to the house faulted underneath his deck. Rather than remove a section of his deck he opted to install a new service line from utility transformer to his meter socket.
The meter socket was very rusted out, so we had him replace it. The electrician found that each single lug for the phase wires has two phase wires in them. One set runs to each of two circuit panels with 100A main breakers.
I don't believe this is acceptable, and was going to have him convert his service on the inside so that one panel acts as the main and feeds the second panel which would act as a sub-panel.
My question is "Does NEC address the double tap in a single lug at a meter socket?". If so, which section? I have not been able to find anything.
Thanks,
Creig
The meter socket was very rusted out, so we had him replace it. The electrician found that each single lug for the phase wires has two phase wires in them. One set runs to each of two circuit panels with 100A main breakers.
I don't believe this is acceptable, and was going to have him convert his service on the inside so that one panel acts as the main and feeds the second panel which would act as a sub-panel.
My question is "Does NEC address the double tap in a single lug at a meter socket?". If so, which section? I have not been able to find anything.
Thanks,
Creig