Has anyone ever heard of an inpector wanting all the circuits that feeds ice and snow melting equipment to have a simutaneous trip and disconnect. An inspector is requiring the 4 two pole breakers feeding the heat trace to be all connected by a breaker handle tie and we say that you can not even buy a handl tie this large. He says that you can install two pole handle ties between the two pole breakers such as one handle tie connecting A and B phase of two seperate 2 pole breakers.....What do you think about that?
Thanks
Bob:-?
Thanks
Bob:-?