We have a set of drawings showing the load side of xfmr giving a detail for duct bank to service entrance gutter. 8-4'' conduits. There is no detail for anyother conduit run that laid underground. We have 6-4'' conduits from SE to MDP2 less than 50' or directly behind service gutter and 2-4'' conduit about 200' to MDP1 . There isnt a detail or notes for this mdp1 or 2 would it be ok to think we can just dig trench and throw in conduit or should we continue the duct bank for mdp1 and 2?
Question #2. If you had a chance to install conduit in foundation before poured concrete would to avoid running overhead? I sometimes find that helpful and PITA especially if I didnt do the work. If I end up on some else job they put to many 90s or didnt glue it right and I end up getting extra work.
Question #2. If you had a chance to install conduit in foundation before poured concrete would to avoid running overhead? I sometimes find that helpful and PITA especially if I didnt do the work. If I end up on some else job they put to many 90s or didnt glue it right and I end up getting extra work.