rayp1
Member
- Location
- Phoenix, Az, USA
Situation: Underground is direct buried, 34.5kV, PVC Sch 80 conduit sweep (just a 90 degree elbow) installed into the termination cabinet. Question: Is a separate equipment grounding conduit required for each conduit sweep? Second question: Is a road sleeve 120 feet or short sleeve (Approx 10 feet) require a EGC in each conduit for direct burial cable applications? Thank you.