I have 13.2kV wye to 600V wye transformer. H0 and X0 bonded and 13.2kV MGN. The 13.2kV 3 incoming concentric neutral cables to transformer is grounded at the transformer and has no EGC. 600V xfmr secondary side has 3 phase and neutral going to swbd which has neutral bar and equipment grounding conductor bar bonded thru system bonding jumper at swbd.
Question does NEC 2014 require 600V AC system to have equipment grounding conductor?
Question does NEC 2014 require 600V AC system to have equipment grounding conductor?