Having 1000a OCPD fed by 4 sets each 4xsingle core 400mm2(4x4x1c400mm2) all in parallel, as per table 250.122 the EGC would be min 70mm2. My college says: for bundle installation, better to have EGC with each bundle, means 4 x1c70mm2 which is extra cost.
My question is, can we split the 1c70mm2 EGC into 4x1c25mm2?