LowSparkHighHealed
Member
This is my first post. I recently ran my deep well water line along with the customary UF cable for it's power connection. Since I was crossing the road I took the opportunity and buried a number of rigid pvc conduits below the road at a higher level. Their spec calls for 2" schedule 80 dropping from the meter socket to a point 18" below finish grade. The transformer pad is at a point directly across this road so it is a straight shot. I currently have a sections of 2" schedule 80 starting near the transformer, going under the road and stopping about 15' from the base of the meter socket. At this point it is basically a protective sleeve. I have a pull rope at both ends. Is this something a utility will work with, should I take it further and complete the conduit bend up into the meter socket or do they prefer to disrupt the road again and trench their own path? TIA