SparkyEst.
Member
- Location
- Northern Indiana USA
I currently work for a large general contractor, and this general contractor has an excavation division, electrical division, concrete division, and carpenter division. As the lead of the electrical division I have been awarded a lot of jobs based on early budgeting/conception to implementation. We do a lot of design builds, so I also do a lot of preliminary/final electrical design to get approved and stamped by engineer. That's a quick synopsis/background.
Here is my question for guys in the same boat, or may have insight, typically if I were a sub-contractor the GC, and the owner or GC made changes I would have change orders processed accordingly. In-house makes that a bit difficult because as the GC our project manager may see the job doing well and decide to hold back the CO to customer and eat the cost themselves. Where that lies a problem with me is that it doesn't then report on the job cost reports I do because there was never a final CO to customer and then it doesn't get entered into my reports. Has anyone else ever had this issue and if so how did you handle it?
Right now I am currently making a excel spreadsheet log of all changes and if I see one that is approved, but doesn't show up on job cost reports then I make note. Ultimately when the owners look at the final cost for the job and see's electrical "lost" or was "over" budget because of the unreported changes by the project manager I essentially have to "throw" them under the bus. I am looking for advice to possibly smooth this transition out and figure a way to get that information across the board, without seeing the customer end of it.
Does this make sense and what are your thoughts?
Here is my question for guys in the same boat, or may have insight, typically if I were a sub-contractor the GC, and the owner or GC made changes I would have change orders processed accordingly. In-house makes that a bit difficult because as the GC our project manager may see the job doing well and decide to hold back the CO to customer and eat the cost themselves. Where that lies a problem with me is that it doesn't then report on the job cost reports I do because there was never a final CO to customer and then it doesn't get entered into my reports. Has anyone else ever had this issue and if so how did you handle it?
Right now I am currently making a excel spreadsheet log of all changes and if I see one that is approved, but doesn't show up on job cost reports then I make note. Ultimately when the owners look at the final cost for the job and see's electrical "lost" or was "over" budget because of the unreported changes by the project manager I essentially have to "throw" them under the bus. I am looking for advice to possibly smooth this transition out and figure a way to get that information across the board, without seeing the customer end of it.
Does this make sense and what are your thoughts?