john37
Senior Member
- Location
- Riverside, California
I was wondering what would be the best way to provide service to the following senario. There is going to be a new service coming out the nearest Manhole with a 1200A 480/277 3ph service going up to the third floor of an industrial bldg. From the manhole there will be a new 750kva utility transformer. My question is it better to put a c.t. can and meter/main or is it better to put a swithgear on the ground floor that will be serving the 3rd floor swithboard? For the 1200A service there is 4-4" conduits with 3 sets of 4 #500mcm. All the equipment has to be Square D according the clients if that matters....Any opinions would be appreciated. Thanks.