Here is a problem that is coming up more and more.
I thought I would see what all you guru's can come up with. I have my own thoughts but collaboration always seems to help.
I have a middle school, 208V, 3 phase , 4 wire service. All grounding and bonding done per NEC. N-G voltage at mains = 0V. A panel fed from main gear has 3V N-G voltage. Some UPS's fed from this panel are going haywire switching back and forth frantically between line power and battery.
What to do?