I have an opportunity to complete an interesting project that has been designed with a 600A service with fused disconnect on the exterior of the building, this feeds an MDP directly behind the disconnect; the MDP feeds 2 - 200A MLO panels, 1 150A MLO panel and 3 large chilers each 100A. The customer amost choked when they seen the equipment cost. My question; can we eliminate the disconnect outside along with the MDP inside and simply feed a wireway from the meter (600A feed through) and drop into the 3 panels (making them MB and the 3 disconnects (fused) ? The panels would be inside opposite the meter. Thanks!