sundowner
Senior Member
- Location
- West Wisconsin
So I'm in a boiler plant with several levels of flooring - all open catwalk, about 15 or so emergency battery back up fixtures moounted throughout. A couplke years back the plant was upgraded and noe the entire facility is backed up with a natgas gen set.
The work order says they'd like the failed Elites replaced. I looked through 700, 701, 702, and beyond a bit. Not sure I have my answer yet - my question is - are they still required to have those E lites in the plant when the entire plant is already backed up and the gen would pick up lighting?
Any thoughts guys??
Thank
Steve
The work order says they'd like the failed Elites replaced. I looked through 700, 701, 702, and beyond a bit. Not sure I have my answer yet - my question is - are they still required to have those E lites in the plant when the entire plant is already backed up and the gen would pick up lighting?
Any thoughts guys??
Thank
Steve