Paul Allen
Electrical Contractor
- Location
- Middleburg Florida
- Occupation
- Electrical Contractor
Hi all, I was approached by a customer about bidding a project to install a emergency power feeder to an office to feed computers, lights and associated equipment from generator power. Problem with the job is that the emergency power is fed off of an emergency generator in a separate building nearby. Both buildings are separate,with separate services, but under the same management.
My statement of work says to disconnect a 100 amp panel feeder off of the existing MDP and connect it to a junction box and feed it from the emergency panel located in a building next door. Provide new conduit wire, breaker etc. etc.
First question that comes to mind is a service disconnect for the emergency panel in the separate building.
I believe we will need to provide one at a minimum, grouped with the normal main disconnect for this building.
My main question though, and the point of my indecision is this. Is there any problems with installing a separate service for this panel with its own disconnect,labeled as being fed from another building on site. Or would good engineering practice require us to install a transfer switch and leave the loads on the existing building service, with emergency power available from the other building EDP to feed the switch in the event of a building outage. I have researched this and don't see any real NEC problems with doing it either way, but my gut is telling me the transfer switch install is the right way to do it. I am really not trying to over engineer the project, but I don't think the way the customer is requesting it to be done is the correct way to do it.
I would like to hear others opinions about how they would approach this
Thank in advance for your help!
Paul Allen
My statement of work says to disconnect a 100 amp panel feeder off of the existing MDP and connect it to a junction box and feed it from the emergency panel located in a building next door. Provide new conduit wire, breaker etc. etc.
First question that comes to mind is a service disconnect for the emergency panel in the separate building.
I believe we will need to provide one at a minimum, grouped with the normal main disconnect for this building.
My main question though, and the point of my indecision is this. Is there any problems with installing a separate service for this panel with its own disconnect,labeled as being fed from another building on site. Or would good engineering practice require us to install a transfer switch and leave the loads on the existing building service, with emergency power available from the other building EDP to feed the switch in the event of a building outage. I have researched this and don't see any real NEC problems with doing it either way, but my gut is telling me the transfer switch install is the right way to do it. I am really not trying to over engineer the project, but I don't think the way the customer is requesting it to be done is the correct way to do it.
I would like to hear others opinions about how they would approach this
Thank in advance for your help!
Paul Allen