We have a Transfer Switch feeding an Emergency SWBD that also feeds an Emergency Panel (EP) and a UPS that in turn feeds a UPS Panel (UP).
Out of the EP and UP there are 2 EMT conduits (One from each panel) that are tied into a Common "J" box and from there a Flex Conduit that has wires from both EP and UP going to 4"(W)x10"(H)x4"(D) module that contains 01 UPS Receptacle and 01 Emergency Receptacle. Is it correct to have those wires in a common "J" box and a Flex conduit?
THank you for your help
Out of the EP and UP there are 2 EMT conduits (One from each panel) that are tied into a Common "J" box and from there a Flex Conduit that has wires from both EP and UP going to 4"(W)x10"(H)x4"(D) module that contains 01 UPS Receptacle and 01 Emergency Receptacle. Is it correct to have those wires in a common "J" box and a Flex conduit?
THank you for your help