So we're hooking up a 225KVA stepup xfmr. 208 delta to 480wye. I've seen articles stating that for the supply side bonding jumper we can simply use the 2" EMT conduit running from the xfmr to the first (service) disconnect with grounding bushings on each end. This just doesn't seem right and seems to conflict with other articles I've read but I'll admit it was in older handbooks. 2020 is on order.
Any clarifications would be appreciated. Unfortunately we already have the wire in the pipe. 4 x 4/0 and it was a b#@$h to pull but it was a tight run and 2 1/2" wouldn't have worked.
Any clarifications would be appreciated. Unfortunately we already have the wire in the pipe. 4 x 4/0 and it was a b#@$h to pull but it was a tight run and 2 1/2" wouldn't have worked.