Had a interesting discussion at our last electrical safety committee about energized work and energized work permits. We have a project where we need to add a MCC bucket to AB line up. We were debating on how to shut the MCC down and one of our seasoned electricians spoke up and indicated he would prefer to put the bucket in hot as going thru the shutdown would expose him to additional risk. He elaborated on the number of disconnects and breakers needed to be opened to accommodate this work and each action was an additional risk for the electrician performing the work. Our SOP for installing a bucket hot requires cat 4 gear & two electricians. In his opinion this was safest approach.
Curious how others feel about this? Is this a valid reason to work the MCC hot? Looking forward to reading your comments.