hjoseph117
Member
- Location
- Amarillo
- Occupation
- Engineer
Small city. First time we have been asked to engineer/stamp a temporary install. We are going about 800ft with 240V single phase. We typically design to 2-3% voltage drop to get to the building (less than 5% to end of branch circuit).
For a temporary install, should we try to stick to 5% or could we increase the voltage drop to save some money on the wire soon to be abandoned? Any recommendations on a good percentage (spoke with electricians in field and they would have done 25% voltage drop back before the city required it to be engineered...)?
For a temporary install, should we try to stick to 5% or could we increase the voltage drop to save some money on the wire soon to be abandoned? Any recommendations on a good percentage (spoke with electricians in field and they would have done 25% voltage drop back before the city required it to be engineered...)?