I had a building department comment on this and the code does not address it in black & white. A 1200A main disconnect feeds a wireway with a #3/0 equipment ground. The wireway has 3 400A tenant meters and disconnects on it. What is the size of the equipment ground from the wireway tap to the line side of the 400A disconnect. NEC 250-122 does not address this other than to say it shall not be required to be larger than the line conductor. Clearly a #3/0 equipment ground is oversized from the wireway tap to the disconnect's line side, but how can I prove it? Thanks, Milton