Traino Electric
Member
- Location
- Palm Beach
I am almost finished with an outside kitchen project. Went for final inspection and I was asked to equipotential bond the kitchen structure. I need to dig it back to pool equipment 170 feet away. Inspector stated it needed to be in pipe 18" underground but he will let me get away with 12".
My question is: do I need to protect the #8 solid in a pipe for the distance between kitchen and pool equipment? And does it have to be 18" underground? Doesn't that defeat the purpose of it? It only is needed to bond gutter on outside kitchen structure. And advice on a different plan is also welcomed. Thanks.
My question is: do I need to protect the #8 solid in a pipe for the distance between kitchen and pool equipment? And does it have to be 18" underground? Doesn't that defeat the purpose of it? It only is needed to bond gutter on outside kitchen structure. And advice on a different plan is also welcomed. Thanks.